Gantt Diagram

The Gantt is described in natural language, using very simple sentences (subject-verb-complement).

Declaring tasks

Tasks defined using square bracket.

Duration

Their durations are defined using the last verb:

@startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
-- All example --
[Task 1 (1 day)] lasts 1 day
[T2 (5 days)] lasts 5 days
[T3 (1 week)] lasts 1 week
[T4 (1 week and 4 days)] lasts 1 week and 4 days
[T5 (2 weeks)] lasts 2 weeks
@endgantt

A week is a synonym for how many non-closed days are in a week. So if you specify Saturday and Sunday as closed, a week will be equivalent to 5 days

Start

Their beginning are defined using the start verb:

@startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days

Project starts 2020-07-01
[Prototype design] starts 2020-07-01
[Test prototype] starts 2020-07-16
@endgantt
@startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days

[Prototype design] starts D+0
[Test prototype] starts D+15
@endgantt

[Ref. for D+nn form: QA-14494]

End

Their ending are defined using the end verb:

@startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days

Project starts 2020-07-01
[Prototype design] ends 2020-07-15
[Test prototype] ends 2020-07-25
@endgantt
@startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days

[Prototype design] ends D+14
[Test prototype] ends D+24
@endgantt

Start/End

It is possible to define both absolutely, by specifying dates:

@startgantt
Project starts 2020-07-01
[Prototype design] starts 2020-07-01
[Test prototype] starts 2020-07-16
[Prototype design] ends 2020-07-15
[Test prototype] ends 2020-07-25

@endgantt
@startgantt
[Prototype design] starts D+0
[Test prototype] starts D+15
[Prototype design] ends D+14
[Test prototype] ends D+24
@endgantt

One-line declaration (with the and conjunction)

It is possible to combine declaration on one line with the and conjunction.

@startgantt
Project starts 2020-07-01
[Prototype design] starts 2020-07-01 and ends 2020-07-15
[Test prototype] starts 2020-07-16 and lasts 10 days
@endgantt

Adding constraints

It is possible to add constraints between tasks.

@startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
[Test prototype] starts at [Prototype design]'s end
@endgantt
@startgantt
[Prototype design] lasts 10 days
[Code prototype] lasts 10 days
[Write tests] lasts 5 days
[Code prototype] starts at [Prototype design]'s end
[Write tests] starts at [Code prototype]'s start
@endgantt

Short names

It is possible to define short name for tasks with the as keyword.

@startgantt
[Prototype design] as [D] lasts 15 days
[Test prototype] as [T] lasts 10 days
[T] starts at [D]'s end
@endgantt

Customize colors

It is also possible to customize link::color[colors] with is colored in.

@startgantt
[Prototype design] lasts 13 days
[Test prototype] lasts 4 days
[Test prototype] starts at [Prototype design]'s end
[Prototype design] is colored in Fuchsia/FireBrick
[Test prototype] is colored in GreenYellow/Green
@endgantt

Completion status

Adding completion depending percentage

You can set the completion status of a task, by the command: * is xx% completed * is xx% complete

@startgantt
[foo] lasts 21 days
[foo] is 40% completed
[bar] lasts 30 days and is 10% complete
@endgantt

Change colour of completion (by style)

@startgantt



[Prototype design] lasts 7 days
[Test prototype 0] lasts 4 days
[Test prototype 10] lasts 4 days
[Test prototype 20] lasts 4 days
[Test prototype 30] lasts 4 days
[Test prototype 40] lasts 4 days
[Test prototype 50] lasts 4 days
[Test prototype 60] lasts 4 days
[Test prototype 70] lasts 4 days
[Test prototype 80] lasts 4 days
[Test prototype 90] lasts 4 days
[Test prototype 100] lasts 4 days

[Test prototype 0] starts at [Prototype design]'s end
[Test prototype 10] starts at [Prototype design]'s end
[Test prototype 20] starts at [Prototype design]'s end
[Test prototype 30] starts at [Prototype design]'s end
[Test prototype 40] starts at [Prototype design]'s end
[Test prototype 50] starts at [Prototype design]'s end
[Test prototype 60] starts at [Prototype design]'s end
[Test prototype 70] starts at [Prototype design]'s end
[Test prototype 80] starts at [Prototype design]'s end
[Test prototype 90] starts at [Prototype design]'s end
[Test prototype 100] starts at [Prototype design]'s end

[Test prototype 0] is 0% complete
[Test prototype 10] is 10% complete
[Test prototype 20] is 20% complete
[Test prototype 30] is 30% complete
[Test prototype 40] is 40% complete
[Test prototype 50] is 50% complete
[Test prototype 60] is 60% complete
[Test prototype 70] is 70% complete
[Test prototype 80] is 80% complete
[Test prototype 90] is 90% complete
[Test prototype 100] is 100% complete

@endgantt

[Ref. QA-8297]

Milestone

You can define Milestones using the happen verb.

Relative milestone (use of constraints)

@startgantt
[Test prototype] lasts 10 days
[Prototype completed] happens at [Test prototype]'s end
[Setup assembly line] lasts 12 days
[Setup assembly line] starts at [Test prototype]'s end
@endgantt

Absolute milestone (use of fixed date)

@startgantt
Project starts 2020-07-01
[Test prototype] lasts 10 days
[Prototype completed] happens 2020-07-10
[Setup assembly line] lasts 12 days
[Setup assembly line] starts at [Test prototype]'s end
@endgantt

Milestone of maximum end of tasks

@startgantt
[Task1] lasts 4 days
then [Task1.1] lasts 4 days
[Task1.2] starts at [Task1]'s end and lasts 7 days

[Task2] lasts 5 days
then [Task2.1] lasts 4 days

[MaxTaskEnd] happens at [Task1.1]'s end
[MaxTaskEnd] happens at [Task1.2]'s end
[MaxTaskEnd] happens at [Task2.1]'s end

@endgantt

[Ref. QA-10764]

You can add hyperlinks to tasks.

@startgantt
[task1] lasts 10 days
[task1] links to [[http://plantuml.com]]
@endgantt

Calendar

You can specify a starting date for the whole project. By default, the first task starts at this date.

@startgantt
Project starts the 20th of september 2017
[Prototype design] as [TASK1] lasts 13 days
[TASK1] is colored in Lavender/LightBlue
@endgantt

Coloring days

It is possible to add link::color[colors] to some days.

@startgantt
Project starts the 2020/09/01

2020/09/07 is colored in salmon
2020/09/13 to 2020/09/16 are colored in lightblue

[Prototype design] as [TASK1] lasts 22 days
[TASK1] is colored in Lavender/LightBlue
[Prototype completed] happens at [TASK1]'s end
@endgantt

Changing scale

You can change scale for very long project, with one of those parameters: * printscale * ganttscale * projectscale and one of the values: * daily (by default) * weekly * monthly * quarterly * yearly

Daily (by default)

@startgantt
saturday are closed
sunday are closed

Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

Weekly

@startgantt
printscale weekly
saturday are closed
sunday are closed

Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
@startgantt
printscale weekly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

Monthly

@startgantt
projectscale monthly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

Quarterly

@startgantt
projectscale quarterly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
@startgantt
projectscale quarterly
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]

2021-01-18 to 2021-03-22 are colored in salmon
@endgantt

Yearly

@startgantt
projectscale yearly
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]

2021-01-18 to 2021-03-22 are colored in salmon
@endgantt

Zoom (example for all scale)

You can change zoom, with the parameter: * zoom <integer>

Zoom on weekly scale

Without zoom

@startgantt
printscale daily
saturday are closed
sunday are closed

Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 8 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 3 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

With zoom

@startgantt
printscale daily zoom 2
saturday are closed
sunday are closed

Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 8 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 3 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

[Ref. QA-13725]

Zoom on weekly scale

Without zoom

@startgantt
printscale weekly
saturday are closed
sunday are closed

Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

With zoom

@startgantt
printscale weekly zoom 4
saturday are closed
sunday are closed

Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

Zoom on monthly scale

Without zoom

@startgantt
projectscale monthly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

With zoom

@startgantt
projectscale monthly zoom 3
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

Zoom on quarterly scale

Without zoom

@startgantt
projectscale quarterly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

With zoom

@startgantt
projectscale quarterly zoom 7
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

Zoom on yearly scale

Without zoom

@startgantt
projectscale yearly
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]

2021-01-18 to 2021-03-22 are colored in salmon
@endgantt

With zoom

@startgantt
projectscale yearly zoom 2
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]

2021-01-18 to 2021-03-22 are colored in salmon
@endgantt

Close day

It is possible to close some day.

@startgantt
project starts the 2018/04/09
saturday are closed
sunday are closed
2018/05/01 is closed
2018/04/17 to 2018/04/19 is closed
[Prototype design] lasts 14 days
[Test prototype] lasts 4 days
[Test prototype] starts at [Prototype design]'s end
[Prototype design] is colored in Fuchsia/FireBrick
[Test prototype] is colored in GreenYellow/Green
@endgantt

Then it is possible to open some closed day.

@startgantt
2020-07-07 to 2020-07-17 is closed
2020-07-13 is open

Project starts the 2020-07-01
[Prototype design] lasts 10 days
Then [Test prototype] lasts 10 days
@endgantt

Definition of a week depending of closed days

A week is a synonym for how many non-closed days are in a week, as:

@startgantt
Project starts 2021-03-29
[Review 01] happens at 2021-03-29
[Review 02 - 3 weeks] happens on 3 weeks after [Review 01]'s end
[Review 02 - 21 days] happens on 21 days after [Review 01]'s end
@endgantt

So if you specify Saturday and Sunday as closed, a week will be equivalent to 5 days, as:

@startgantt
Project starts 2021-03-29
saturday are closed
sunday are closed
[Review 01] happens at 2021-03-29
[Review 02 - 3 weeks] happens on 3 weeks after [Review 01]'s end
[Review 02 - 21 days] happens on 21 days after [Review 01]'s end
@endgantt

[Ref. QA-13434]

Simplified task succession

It’s possible to use the then keyword to denote consecutive tasks.

@startgantt
[Prototype design] lasts 14 days
then [Test prototype] lasts 4 days
then [Deploy prototype] lasts 6 days
@endgantt

You can also use arrow ->

@startgantt
[Prototype design] lasts 14 days
[Build prototype] lasts 4 days
[Prepare test] lasts 6 days
[Prototype design] -> [Build prototype]
[Prototype design] -> [Prepare test]
@endgantt

Working with resources

You can affect tasks on resources using the on keyword and brackets for resource name.

@startgantt
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days
then [Task3] on {Alice:25%} lasts 1 days
@endgantt

Multiple resources can be assigned to a task:

@startgantt
[Task1] on {Alice} {Bob} lasts 20 days
@endgantt

Resources can be marked as off on specific days:

@startgantt
project starts on 2020-06-19
[Task1] on {Alice} lasts 10 days
{Alice} is off on 2020-06-24 to 2020-06-26
@endgantt

Hide resources

Without any hiding (by default)

@startgantt
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days
then [Task3] on {Alice:25%} lasts 1 days
then [Task4] on {Alice:25%} {Bob} lasts 1 days
@endgantt

Hide resources names

You can hide ressources names and percentage, on tasks, using the hide ressources names keywords.

@startgantt
hide ressources names
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days
then [Task3] on {Alice:25%} lasts 1 days
then [Task4] on {Alice:25%} {Bob} lasts 1 days
@endgantt

Hide resources footbox

You can also hide ressources names on bottom of the diagram using the + hide ressources footbox+ keywords.

@startgantt
hide ressources footbox
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days
then [Task3] on {Alice:25%} lasts 1 days
then [Task4] on {Alice:25%} {Bob} lasts 1 days
@endgantt

Hide the both (resources names and resources footbox)

You can also hide the both.

@startgantt
hide ressources names
hide ressources footbox
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days
then [Task3] on {Alice:25%} lasts 1 days
then [Task4] on {Alice:25%} {Bob} lasts 1 days
@endgantt

Separator

You can use -- to separate sets of tasks.

@startgantt
[Task1] lasts 10 days
then [Task2] lasts 4 days
-- Phase Two --
then [Task3] lasts 5 days
then [Task4] lasts 6 days
@endgantt

Complex example

It also possible to use the and conjunction.

You can also add delays in constraints.

@startgantt
[Prototype design] lasts 13 days and is colored in Lavender/LightBlue
[Test prototype] lasts 9 days and is colored in Coral/Green and starts 3 days after [Prototype design]'s end
[Write tests] lasts 5 days and ends at [Prototype design]'s end
[Hire tests writers] lasts 6 days and ends at [Write tests]'s start
[Init and write tests report] is colored in Coral/Green
[Init and write tests report] starts 1 day before [Test prototype]'s start and ends at [Test prototype]'s end
@endgantt

Comments

As is mentioned on link::commons#560kta2oz3a2k362kjbm[Common Commands page]: > Everything that starts with simple quote ' is a comment. > > You can also put comments on several lines using /' to start and '/ to end. (i.e.: the first character (except space character) of a comment line must be a simple quote ')

@startgantt
' This is a comment

[T1] lasts 3 days

/' this comment
is on several lines '/

[T2] starts at [T1]'s end and lasts 1 day
@endgantt

Using style

Without style (by default)

@startgantt
[Task1] lasts 20 days
note bottom
  memo1 ...
  memo2 ...
  explanations1 ...
  explanations2 ...
end note
[Task2] lasts 4 days
[Task1] -> [Task2]
-- Separator title --
[M1] happens on 5 days after [Task1]'s end
-- end --
@endgantt

With style

You can use link::style-evolution[style] to change rendering of elements.

@startgantt

[Task1] lasts 20 days
note bottom
  memo1 ...
  memo2 ...
  explanations1 ...
  explanations2 ...
end note
[Task2] lasts 4 days
[Task1] -> [Task2]
-- Separator title --
[M1] happens on 5 days after [Task1]'s end
-- end --
@endgantt

With style (full example)

@startgantt

Project starts the 2020-12-01

[Task1] lasts 10 days
sunday are closed

note bottom
  memo1 ...
  memo2 ...
  explanations1 ...
  explanations2 ...
end note

[Task2] lasts 20 days
[Task2] starts 10 days after [Task1]'s end
-- Separator title --
[M1] happens on 5 days after [Task1]'s end



-- end --
@endgantt

[Ref. QA-13570, QA-13672]

[[#00D700#DONE]] Thanks for style for Separator and all style for Arrow (thickness…​)

Clean style

With style, you can also clean a Gantt diagram (showing tasks, dependencies and relative durations only - but no actual start date and no actual scale):

@startgantt


hide footbox
[Test prototype] lasts 7 days
[Prototype completed] happens at [Test prototype]'s end
[Setup assembly line] lasts 9 days
[Setup assembly line] starts at [Test prototype]'s end
then [Setup] lasts 5 days
[T2] lasts 2 days and starts at [Test prototype]'s end
then [T3] lasts 3 days
-- end task --
then [T4] lasts 2 days
@endgantt

[Ref. QA-13971]

Or:

@startgantt


hide footbox
project starts the 2018/04/09
saturday are closed
sunday are closed
2018/05/01 is closed
2018/04/17 to 2018/04/19 is closed
[Prototype design] lasts 9 days
[Test prototype] lasts 5 days
[Test prototype] starts at [Prototype design]'s end
[Prototype design] is colored in Fuchsia/FireBrick
[Test prototype] is colored in GreenYellow/Green
@endgantt

[Ref. QA-13464]

Add notes

@startgantt
[task01] lasts 15 days
note bottom
  memo1 ...
  memo2 ...
  explanations1 ...
  explanations2 ...
end note

[task01] -> [task02]

@endgantt

Example with overlap.

@startgantt
[task01] lasts 15 days
note bottom
  memo1 ...
  memo2 ...
  explanations1 ...
  explanations2 ...
end note

[task01] -> [task02]
[task03] lasts 5 days

@endgantt
@startgantt

-- test01 --

[task01] lasts 4 days
note bottom
'note left
memo1 ...
memo2 ...
explanations1 ...
explanations2 ...
end note

[task02] lasts 8 days
[task01] -> [task02]
note bottom
'note left
memo1 ...
memo2 ...
explanations1 ...
explanations2 ...
end note
-- test02 --

[task03] as [t3] lasts 7 days
[t3] -> [t4]
@endgantt

[[#c0ffc0#DONE]] Thanks for correction (of #386 on v1.2020.18) when overlapping

@startgantt

Project starts 2020-09-01

[taskA] starts 2020-09-01 and lasts 3 days
[taskB] starts 2020-09-10 and lasts 3 days
[taskB] displays on same row as [taskA]

[task01] starts 2020-09-05 and lasts 4 days

then [task02] lasts 8 days
note bottom
  note for task02
  more notes
end note

then [task03] lasts 7 days
note bottom
  note for task03
  more notes
end note

-- separator --

[taskC] starts 2020-09-02 and lasts 5 days
[taskD] starts 2020-09-09 and lasts 5 days
[taskD] displays on same row as [taskC]

[task 10] starts 2020-09-05 and lasts 5 days
then [task 11] lasts 5 days
note bottom
  note for task11
  more notes
end note
@endgantt

Pause tasks

@startgantt
Project starts the 5th of december 2018
saturday are closed
sunday are closed
2018/12/29 is opened
[Prototype design] lasts 17 days
[Prototype design] pauses on 2018/12/13
[Prototype design] pauses on 2018/12/14
[Prototype design] pauses on monday
[Test prototype] starts at [Prototype design]'s end and lasts 2 weeks
@endgantt

You can change link colors: * with this syntax: with <color> <style> link

@startgantt
[T1] lasts 4 days
[T2] lasts 4 days and starts 3 days after [T1]'s end with blue dotted link
[T3] lasts 4 days and starts 3 days after [T2]'s end with green bold link
[T4] lasts 4 days and starts 3 days after [T3]'s end with green dashed link
@endgantt
  • or directly by using arrow style

@startgantt

[Prototype design] lasts 7 days
[Build prototype] lasts 4 days
[Prepare test] lasts 6 days
[Prototype design] -[#FF00FF]-> [Build prototype]
[Prototype design] -[dotted]-> [Prepare test]
Then [Run test]  lasts 4 days
@endgantt

[Ref. QA-13693]

Tasks or Milestones on the same line

You can put Tasks or Milestones on the same line, with this syntax: * [T|M] displays on same row as [T|M]

@startgantt
[Prototype design] lasts 13 days
[Test prototype] lasts 4 days and 1 week
[Test prototype] starts 1 week and 2 days after [Prototype design]'s end
[Test prototype] displays on same row as [Prototype design]
[r1] happens on 5 days after [Prototype design]'s end
[r2] happens on 5 days after [r1]'s end
[r3] happens on 5 days after [r2]'s end
[r2] displays on same row as [r1]
[r3] displays on same row as [r1]
@endgantt

Highlight today

@startgantt
Project starts the 20th of september 2018
sunday are close
2018/09/21 to 2018/09/23 are colored in salmon
2018/09/21 to 2018/09/30 are named [Vacation in the Bahamas]

today is 30 days after start and is colored in #AAF
[Foo] happens 40 days after start
[Dummy] lasts 10 days and starts 10 days after start

@endgantt

Task between two milestones

@startgantt
project starts on 2020-07-01
[P_start] happens 2020-07-03
[P_end]   happens 2020-07-13
[Prototype design] occurs from [P_start] to [P_end]
@endgantt

Grammar and verbal form

Verbal form Example

[T] starts

[M] happens

@startgantt

header some header

footer some footer

title My title

[Prototype design] lasts 13 days

legend
The legend
end legend

caption This is caption

@endgantt

(See also: link::commons[Common commands])

Removing Foot Boxes (example for all scale)

You can use the hide footbox keywords to remove the foot boxes of the gantt diagram (as for link::sequence-diagram[sequence diagram]).

Examples on:

  • daily scale (without project start)

@startgantt

hide footbox
title Foot Box removed

[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
@endgantt
  • daily scale

@startgantt

Project starts the 20th of september 2017
[Prototype design] as [TASK1] lasts 13 days
[TASK1] is colored in Lavender/LightBlue

hide footbox
@endgantt
  • weekly scale

@startgantt
hide footbox

printscale weekly
saturday are closed
sunday are closed

Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
  • monthly scale

@startgantt

hide footbox

projectscale monthly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
  • quarterly scale

@startgantt

hide footbox

projectscale quarterly
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]

2021-01-18 to 2021-03-22 are colored in salmon
@endgantt
  • yearly scale

@startgantt

hide footbox

projectscale yearly
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]

2021-01-18 to 2021-03-22 are colored in salmon
@endgantt

Language of the calendar

You can choose the language of the Gantt calendar, with the language <xx> command where <xx> is the ISO 639 code of the language.

English (en, by default)

@startgantt
saturday are closed
sunday are closed

Project starts 2021-01-01
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

Deutsch (de)

@startgantt
language de
saturday are closed
sunday are closed

Project starts 2021-01-01
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

Japanese (ja)

@startgantt
language ja
saturday are closed
sunday are closed

Project starts 2021-01-01
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

Chinese (zh)

@startgantt
language zh
saturday are closed
sunday are closed

Project starts 2021-01-01
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

Korean (ko)

@startgantt
language ko
saturday are closed
sunday are closed

Project starts 2021-01-01
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]

2021-01-18 to 2021-01-22 are colored in salmon
@endgantt

Delete Tasks or Milestones

You can mark some Tasks or Milestones as deleted instead of normally completed to distinguish tasks that may possibly have been discarded, postponed or whatever.

@startgantt
[Prototype design] lasts 1 weeks
then [Prototype completed]  lasts 4 days
[End Prototype completed] happens at [Prototype completed]'s end
then [Test prototype] lasts 5 days
[End Test prototype] happens at [Test prototype]'s end

[Prototype completed] is deleted
[End Prototype completed] is deleted
@endgantt

[Ref. QA-9129]